New Office Network Installation Checklist: From Site Survey to Handover

A tidy office network installation runs in five stages: site survey, design, installation, testing, and handover. This checklist details what is done and what you need to prepare at each stage.

SEO and Content Specialist

5 min read

A data center hall with a white floor and server racks

Short answer: a new office network installation runs in five stages: site survey (measuring the building and the needs of each room), design (routes, equipment, schedule), installation (cable, fiber, equipment, wireless points), testing and tidying (every point is tested and labeled), and handover (floor plan, configuration, handover record). For a mid-sized office, the whole process generally takes 3 to 6 weeks.

Moving offices, opening a branch, or renovating a floor is the ideal time to set up the network properly. Once the ceiling is closed and the desks are in place, every change costs more and disrupts more. This checklist is organized by stage, with two sides: what the installer does, and what you need to prepare so that stage is not delayed.

Overview of the five stages

StageWhat is doneWhat you prepareEstimated time
Site surveyMeasuring the site, checking routes, listing the needs of each roomBuilding floor plan, access to the areas, estimated users per room2-5 working days
DesignNetwork design, equipment list, work stagesApproval of the design and schedule3-5 working days
InstallationPulling cable and fiber, installing panels, equipment, wireless pointsA working time window in the areas being installed1-3 weeks
Testing and tidyingTesting each point, tidying routes, labeling, setting up network segmentationAccess for testing2-5 working days
HandoverRoute floor plan, configuration documentation, explanation to the teamA person in charge on your side1-2 working days
Illustration: office network

1. Site survey

The survey determines almost everything that follows. The checklist to be answered at this stage:

  • Number of users and devices per room, including printers, meeting room equipment, and CCTV.
  • Location of the server room or network rack, with its power and ventilation.
  • Routes available for cable: ceiling, floor, walls, and routes between floors.
  • Wall materials and obstructions that affect the wireless signal.
  • The point where internet enters from the service provider.
  • Growth plan: how many additional people in two to three years.

2. Design and quotation

The design turns survey results into decisions: which points use LAN cable, which routes use fiber optic, and where wireless access points are installed. A guide to choosing among the three is in the article LAN Cable, Fiber Optic, or Wireless for the Office.

Check the design with these questions before approving it:

  • Is the guest network separated from the employee network?
  • Are devices such as CCTV and printers on a network of their own?
  • Are there spare cable points for growth?
  • Where is the firewall installed, and how is remote access (VPN) set up?
  • Which equipment needs to be purchased, and in whose name?

3. Installation

Installation is the most visible stage and the one that disrupts office activity the most. Schedule it with building management, especially when the work is done in an office that is in use. What to confirm during installation:

  • Power cables and data cables run on separate routes to reduce interference.
  • Cables are pulled along tidy routes that are easy to trace, not simply pushed through.
  • Network equipment is mounted in a rack, not left on the floor or inside a cabinet without ventilation.

4. Testing and tidying

Every point is tested before it is declared done, not just tried to see whether the internet turns on. At this stage routes are tidied, every point and port is labeled, and network segmentation (for example guest, employee, and device networks) is configured. Ask for the test results per point in writing.

5. Handover

A tidy network shows its value when there is a fault or a point needs to be added. The documents you should receive:

  1. Route floor plan of cable and fiber on each floor, with the positions of panels and wireless points.
  2. List of points and labels: point number, its room, and the panel port it connects to.
  3. Test results for each point.
  4. Equipment configuration: network segmentation, firewall and VPN rules, and a backup of the configuration.
  5. Handover Record: a list of the work handed over and the start of the warranty period.

Also make sure admin access to all equipment is handed to the company, not only known to the installer.

The most common mistakes

  • Skipping the survey because “the office is small”. The result is misplaced access points and too few cable points in the room that turns out to be busiest.
  • Buying equipment before the design is done. Equipment bought in a hurry often does not match the need for network segmentation or the number of ports.
  • Not leaving spare points. Adding one point after the ceiling is closed can be more trouble than installing ten points at the start.
  • Testing only that “the internet is on”. A connected point is not necessarily stable; written per-point testing is what proves it.
  • Handover without documents. Without the floor plan and configuration, the next repair starts with guessing.

How Legia does it

In the Office Network Installation service, the five stages above are carried out by Legia’s own technicians, not partners, including the firewall and VPN. The whole process generally takes 3 to 6 weeks and ends with the five handover documents above. The coverage area is all of Indonesia, with priority for the Greater Malang area and Java. Active equipment is purchased in your company’s name, and internet subscription fees are separate from the work.

Frequently asked questions

Can installation be done while the office stays in operation?

Yes, with a schedule agreed per area. The most disruptive work, such as pulling cable in the ceiling of work areas, can be scheduled outside working hours or done room by room in turns.

When should the survey be done when moving offices?

Before the interior renovation is finished. Cable routes are easiest to install before the ceiling and partitions are closed.

Is Wi-Fi alone not enough for a new office?

For a small office, it can be enough. Signs of when cable points are needed are discussed in the article Is Wi-Fi Alone Enough for an Office Without LAN Cable?

Who holds the equipment passwords after handover?

Your company. Admin access and configuration are handed over together with the handover documents, so the network can still be managed even if the installer changes.